Out of the different contracts the Engineering procurement and
construction contract (EPC)follows the most common project finance path. In the EPC contract the contractor is
entrusted with the obligation to build and deliver the project facilities on
a turnkey basis. In these type of contract the contract is awarded to a well
established and resourceful contractor who has thorough knowledge about the project
on a lump sum fixed price . The price is based on acceptance of a certain specifications,
and with certain performance warranties. In the EPC contract the completion
date of the project and the effective date of the contract plays very vital
role.Is quite complicated in terms of legal issue, therefore the project
company and the EPC contractor need sufficient experience and knowledge of the
nature of project to avoid their faults and minimize the risks during contract
execution.
The terms EPC contract and turnkey contract are interchangeable.
EPC stands for engineering (design), procurement and construction. In the Turnkey
contract the owner of the project provides some basic agreed facilities and
rest of the remaining works of the projects are to be carried out by the
contractors and hand over the project to the owner in such a way that l it will
need to be done by the owner to do is
turn the key and the facility will function as intended. Alternative forms of
construction contract are a project management approach and alliance
contracting. Basic contents of an EPC contract are:
·
Description of the project
·
Price
·
Payment
·
Completion date
·
Completion guarantee and Liquidated damages:
·
Performance guarantee and LDs
·
Cap under LDs
Decription of the project: Every project is described prior to
fixing of the price of the project cost. In case of Thermal power plant the
capacity of the plant to be produced in terms of MW and how many units, what
are all the major systems to be provided in place . further project description
narrates what is the specification for major equipments ,process guarantees,
time of completion are specified
600 MW Thermal Power Plant
Price on EPC contracts are decided as single lump sum price for
completion of the entire project.. Since EPC contracts are voluminous in nature
with long duration from date of beginning
to date of commercial operation of the project the price is divided as design
and engineering component price,cost for supply of the materials with specified
terms and for civil and site services a separate price.. The price is always
linked with certain important deliveries of equipments and in case of site
services with completion dates of major mile stones.
Payment : Even though price is fixed separately for design and engineering, supply of equipments
,civil and site services the contractor must be provided with free access to
collect the money on completion of certain activities. In order to facilitate
this the payment terms are framed in the contract when the payment must be made
to the contractor and what percentage of money to be released. It is further
discussed among the contractor and owner and billing break up is agreed. Based
on which the contractor gets his money on completion of the obligations
Always the payment done by the owner to the contractor is
safeguarded by an agreed project completion schedule with starting date or
effective date of the contract and completion date of the contract. Theses two
mile stones are most important and all the other intermittent activities can be
adjusted to achieve the final date. The schedule thus prepared is called
project schedule and being followed by every one of the project to achieve the
final date of completion in a successful way.
In the contract agreed between the owner and the contractor it
is very clearly mentioned the liquidated damages not in form of penalty to be
paid by the contractor to the owner in case if the contract is not fulfilled as
agreed. However the penalty is applicable only it is legally proved by the
owner that the obligations mentioned in the contract are not properly carried
out. Normally in power projects the liquidated damages are imposed for the
performance of the equipments supplied by the contractor in terms of heat rate
to be met by the contractor along with auxiliary power consumption. Another type
of liquidated damage is for the delay in completion of the project due to the
fault of the contractors .
There is always a cap agreed and mentioned in the contract for the delay and performance
in terms of money which is prefixed while siging the contract
No comments:
Post a Comment