The
first step when an estimator start his costing of erection work is to find out
how much direct manpower is to be employed from starting of the project work up
to completion of the works as specified on the contract document. In general the
detail description of the works to be completed is clearly mentioned in the
request for quotation document(RFQ).Many a cases a detailed bill of quantities(BOQ)
are also attached with the (RFQ).Based on the bill of quantity the direct
manpower cost is calculated. Direct manpower means leaving the supervisory
staff for that work the required number of labourers required in various categories.
These people are. Mostly in the capacity of technicians like welders, Fitters,
khalasis,Riggers and helpers in case of mechanical erection works. For civil
works the calculation will be for masons for masonry work, carpenters, bar benders,
and. helpers. Similarly the direct manpower for electrical and instrumentation works
will be qualified electricians for HT and electricians who can handle LT works
and along with tem the number of helpers required for assisting the technicians.
Fitters are further categorised in India as fabricator and fitter.
The
welders are costlier and difficult to get commodities in construction sites
since there presence will be required in every step when work progresses. In welders
too there are welders qualified for working in steel ,pipeline works. .Welders
working in pipe line construction works have lot of further sub categories .The
welders qualified for different position welding in pipe works and they get
paid according to their capability. The materials of construction in pipe works
are many. Carbon steel pipe line works, alloy steel pipe line works, stainless
steel pipeline works etc.All the welders cannot work in all kinds of materials.
They need to be qualified for different positions and for different materials. The
welders .who can only work in structural steel works are called as structural
steel welders. The helpers of the welders get their training under the
supervision of the elder while on work and become a structural welder and
further get him qualified in other fields.
Project
construction is a voluminous field which involves shifting and lifting of
materials. The lifting and shifting of the materials can either be done my machinery
or by manpower. Even though mostly machineries are used for shifting and
lifting the presence of manpower becomes inevitable in certain cases where in congested
areas machineries cannot be operated. The persons helping in such activities
are called as Riggers and experienced riggers are termed as sarongs. The
juniors who work with the help of sarongs are called as khalasis
..In
electrical works electricians are the persons who can check up wiring in panels.
Technicians who works in electrical works are used for termination of wires,
give connection to rotary equipments. In electrical works riggers are mainly
used for the laying of cables underground and on trays, erection of electrical
panels etc.The electrical works also the involvement of welders, fitters are there.
Fitter works on installation of cable trays and cable tray supports. Welder
helps them in fixing the cable trays where ever required. The panel supports are
mostly site made and fabricated at site.
Instrumentation
works also have similar sequence of operations like cable tray fixing, laying
of cables, installation of junction boxes, cable termination where again the described
technicians comes into picture. So it becomes necessary for the estimator to
understand the work involvement and actual requirement of people of different disciplines.
Without understanding and not knowing the quantum of work involvement the
estimation will not be accurate. Based on the bill of quantity and with the
experience of the estimator the total requirement of direct manpower is
calculated. The basis of calculation of direct manpower is productivity.
For productivity please see my next post