In my Blog i would like to
describe the general procedure for preparation of quotation when the company
receive the enquiry from the client. Initially the received bid is thou roughly
scrutinised for the worth of quoting the bid. The nature and financial
involvement is assessed by viewing the bid. The bid may be a normal Labour
contract, only a small infra structure civil contract, only a part package of
the project , may be either Engineering,Procurement and construction project or
a normal erection contract .
Labour contracts :Every
company in India have their own policies in selection of the work for
execution. Some contracting companies
wish to participate in all works of construction. It may be a civil contract,
mechanical contract, electrical contract others which is purely construction in
nature. This means whatever materials related to the construction activities
either consumables or construction materials every item will be supplied by the
client. Only labour portion of the contract will be carried out by the
contracting company. The contract value of which will be very less. The
contractors who have labours under their control wishes to execute such bids.
Bigger companies with their own resources don’t wish to participate in such
bids
LABOUR CONTRACTOR WITH
WORKERS
Civil contracts :
When the owner wishes to control the cost of the project normally the infr tructure facilities like local roads( Temperorary in nature) to be provided
for their Engineering, rocurement and contraction contractor ,they develop the
facilities with their own officers and only hiring a medium sized contractor
who can carry out such projects ( Mostly from local area) are selected. In such
cases the civil materials like bricks, sand,rebar,metal etc.According to
clarifications ,contractors are classified as Class A,B,C based on their resources
and financial capabilities. When the work starts the design and darwings required
for execution of the works are normally prepared by the design and engineering
contractor selected by the owner of the project and the execution at site is
being carried out by the officers of the owner.
Buil Building Contractor
Packaging Route :
Certain clients having sufficient workforce implements the project on package route. It means the major equipments and material procurement actions are taken
care by the owner himself and units forming part of the project which are
readily available in market with sufficient experience in that particular field
are purchased by owner. In the presence of the representative of the package
supplier the client himself hire a small contractor and under the guidance of
package vendor the contractor completes the works of the package. Normally the
value of contracts are normally less except for major erections like boilers of
higher capacity. Based on the size and capacity of the package the client
choose a contractor who has sufficient experience in that particular field
along with financial capabilities. In case
the client wants to capture good reputed contractors for installation
they combine major packages together to increase the contract value of the
installation.
Erection Contracts :
When big factories are set up for the production of power, fertilizer
,petrochemicals and ore beneficiation plants the volume of items to be
installed are huge and many and in most of the cases such items can not be
handled by client himself. Hence it becomes absolutely necessary for him to
engage a standard contractor to carry out major installation works. The
erection works are complex in nature and involves installation of many items
like structural steel, Heavy equipments, rotary equipments, pipe line works
with various materials of construction . To handle such a big volume of work it
may not possible either by a small or a medium sized contractor. Hence the
client/ owner has no option except to select a contractor with good financial
capability along with their own major resources to execute the work in time
with quality. Contracts of that nature
are being handled by big contracting companies in the country.
Read my next post regarding cost estimation of Erection
contracts